Week | Topic | Readings/ | Comments |
---|---|---|---|
Starting | Chapters | ||
09/04 | Introduction | ||
Resource Management | |||
09/09 | Equipment Productivity | Chapter 14 | |
Equipment Ownership | Chapter 13 | ||
09/16 | Labor Management | Chapter 15 | |
Material Management | Chapter 18 | ||
09/23 | Site and Operation Design | Test 1 | |
Project Management | |||
09/30 | Scheduling Methods | Chapter 8 | |
10/07 | Cost Estimating | Chapter 16 | |
10/14 | Cash flow | Chapter 11 | |
10/21 | Cost Control | Chapter 17 | Test 2 |
Project Organization | |||
10/28 | Contracts and Risk Management | Chapter 4 | |
11/04 | Delivery Systems | Chapter 4 | |
Advanced Topics | |||
11/11 | Information Modeling | Handouts | |
11/18 | Construction Simulations | Handouts | No class on 11/22 |
12/02 | Contingency Management | Handouts | |
12/09 | Legal Issues | Handouts | Test 3 |